Advertisement

Easement and Contract: The Legalities of Trenchless Projects

By Tabitha Mishra
Published: October 9, 2020 | Last updated: July 5, 2023
Key Takeaways

Easement is basically an agreement between the landowner and the contractor for use of the owners land for a specific period of time. Easements can be temporary or permanent.

Now that contractors and the general public are becoming aware of the benefits of trenchless technology for the purpose of pipeline and cable installation, the use of trenchless construction and rehabilitation methods are on the rise.

Advertisement

To start off on the right foot, it's important to ensure you have selected the right trenchless method for your project needs. Our Trenchless Methods Calculator will help, by providing you with detailed recommendations, customized just for you.

Not only do trenchless projects involve less time and minimal disruption, but they also provide an effective solution for issues relating to land acquisition. Legalities related to any construction project are always challenging and need to be dealt with before a project is begun, to minimize loss in terms of time and money.

Advertisement

Legal issues not only take up money, they also take a lot of time once caught in the crosshairs of the legal system. Time lost in a construction project is a financial loss in terms of hired workers and machinery, in addition to fines imposed for overshooting project deadlines. The first step to a successful trenchless project is planning. (Read also: The Planning Process: How to Prepare for a Successful Trenchless Construction Project.)

Easements

The most challenging part of the planning phase is land easement acquisition. Thanks to trenchless technology, landowners are more comfortable handing over their land to a contractor.

An easement is basically an agreement between the landowner and the contractor for use of the owners' land for a specific period of time. Easements can be temporary or permanent. Permanent land acquisition may be required where permanent structures such as valve chambers or block valve stations and manholes, related to the project will have to be erected.

Temporary easements will have to be acquired when the land has to be used for allowing activities related to construction and installation like creating entry and exit shafts for the purpose of placing materials, machinery and workers for carrying out the project.

Sometimes in temporary easement there may be a need to move structures if any are over the planned route. Costs related to land easement are usually made during the analysis stage, however; delays related to easement, indirect costs and legal issues should also be considered.

Advertisement

Based on state guidelines, land acquisition is done either as "Acquisition by agreement" or "Compulsory acquisition". Before compulsory acquisition is resorted to, all means to reasonably negotiate with the landowner are undertaken.

Once the land requirements are identified by the council dealing with such matters, the landowners are contacted with a letter requesting access for a council appointed valuer to the land for the purpose of assessing compensation payable to the owner. If the landowner permits access, a negotiable deal is offered based on the valuer's assessment. (Read also: Why Trenchless Construction is Ideal for Historical Towns.)

Once the deal is finalized, the owner makes an agreement either to acquire an easement or to acquire land for public purposes. Further legal procedures are to be followed depending on the agreement.

Contracts

As with all construction projects, trenchless projects also involve many phases and activities. All these activities though interconnected, need different types of suppliers, equipment and skills. Relying on a single contractor for the purpose of executing an entire project can prove to be a disaster.

It is the responsibility of the project manager to appoint a contract officer for the purpose of employing different contractors, to work in coordination, under his jurisdiction, to complete the project.

Prior to commencing the search for contractors, a cost analysis is carried out to determine a negotiable position that permits the contracting officer and the contractor to reach a reasonable price. It rests on the contracting officer’s best judgment to negotiate either within the quoted price or to stretch it further so as to reasonably accommodate the contractor's deal because the contracting officer knows the actual price that the government will pay.

A contracting officer may have to consider many factors while selecting contractors and negotiating. To get the best contractor for a project, a fixed price deal with effective price competition will result in realistic pricing, for which price analysis can provide the basis for selecting the type of contract.

When price analysis is insufficient or when there is ineffective price competition, the basis of negotiation is taken to be the cost estimate of the government or the company offering the contract. As far as possible the contracting officer tries to establish a fixed price contract for the entire contract unless unforeseen changes are expected or performance uncertainties make it difficult to estimate costs in advance.

In some cases, such as when a project has to be urgently completed, the Government may shoulder the greater risk and may also offer incentives to ensure the project is completed on time.

The contract price includes project cost, profit, and overhead expenses imposed by the contractor. This cost should be legally documented and should be binding between the owner and the contractor.

Contracts are awarded either through the bidding process or by negotiating. During the bidding phase, detailed plans and estimates are submitted by the engineering department, however; once the work is completed, the selected contractor is paid based on the actual quantities of work. (Read also: How to Bid on That Trenchless City Project.)

Sometimes owners do not undertake the bidding process; rather employ a more flexible pricing arrangement by selecting their own contractors and negotiating with them. These contractors are often those that have successfully worked for the owner previously, or have an excellent track record.

Four different types of contracts are used:

Fixed Price Contracts

This includes all the costs related to the construction activity and may include benefits for early completion or penalties for delay in the project. This contract is generally used when the scope and cost of work are clear. The risk is on the contractor’s side, and that should be taken into account at the time of negotiation.

Cost-plus Contract

This involves payment of incurred cost from construction activity either as direct or indirect cost. Overheads and profits have to be specifically mentioned by the contractor in a pre-negotiated amount. This contract is applied when the scope of work is undefined.

Time and Material Contracts

This involves an agreement between the owner and the contractor for an hourly or daily rate including additional expenses. This contract is used when the scope of work is not clear.

Unit Price Contracts

This type of contract has a predetermined set of quantities that have been priced, which enables the owner to check for price inflation of services or goods that he is hiring. Unit pricing can be adjusted when there is a change in scope of work.

Final Thoughts

Trenchless technology has made construction related legalities, especially those related to acquiring land for easement much easier than those associated with open cut installation projects.

It also causes minimal excavation of ground surface and helps in relatively quicker completion of construction activities. Knowing legal formalities and implication are essential to complete a project in the given time frame.

Often delayed projects are a result of incomplete legal paperwork and incorrect methods of acquiring land for easement or purchase. Hiring a legal consultant well versed with related issues can ease the legal burden from any construction project and ensure timely completion.

Share This Article

  • Facebook
  • LinkedIn
  • Twitter

Written by Tabitha Mishra | Civil Engineer, Technical Content Writer

Tabitha Mishra

Tabitha has a Bachelors Degree in Civil Engineering from Mumbai University, India, and is currently freelancing as a technical content writer. Prior to writing, she has worked as a site engineer and site manager for various building construction, building rehabilitation, and real estate evaluation projects.

Tabitha is also certified as a Primavera project management professional and is well versed with Auto CAD. In her spare time, she does private consultation for small-sized home builders and assists with plans and permissions.

Related Articles

Go back to top