Advertisement

Utility Tunneling Vs. Pipe Jacking Trenchless Construction Methods

By Tabitha Mishra
Published: April 8, 2019 | Last updated: July 5, 2023
Key Takeaways

To make an informed decision that will be beneficial for the owner, the contractor and the client, it’s important to understand how these different trenchless construction methods work.

There are many trenchless construction methods that can be selected based on prevalent geological conditions and type of project. It is advisable to understand how different trenchless construction methods work in order to make an informed decision that will be beneficial for the owner, the contractor and the client.

Advertisement

Here we will take a look at utility tunneling and pipe jacking, and try to understand them better.

Understanding Pipe Jacking and Utility Tunneling Methods

Pipe jacking and utility tunneling are different trenchless methods, however; they are similar in that both require entry for workers to carry out soil excavation. (Read An Overview of Hydrovac Excavation.)

Advertisement

Pipe Jacking

A casing pipe is directly jacked into the ground behind a jacking shield. The pipe forms the lining for the borehole. Since thrust force increases with pipe length, intermediate jacking stations (IJS) have to be constructed for long drives.

Jacking pipes are made of steel, glass-reinforced polymer mortar, reinforced concrete or vitrified clay. The casing pipe can also act as the carrier pipe if so designed. If a separate carrier pipe is to be installed, the pipe can be of any material including high density polyethylene (HDPE) and polyvinyl chloride (PVC). (Want to know more? Here's Everything You Need to Know About Pipe Jacking.)

Utility Tunneling

The shield is pushed forward by hydraulic rams, which are later retracted to manually install liners in the cut section. Once the soil is excavated and the liner is installed, hydraulic jacks are leveraged against the installed liners in order to push the shield forward and the process is repeated.

Free Download: Geotechnical Site Investigations: Your Ultimate Guide to Identifying Project Risks

Advertisement

The thrust force is almost negligible because liners are not pushed into place. The carrier pipe installed should be of sufficient strength to be able to withstand earth loads and forces during grouting of annular space that the pipe may encounter. Soil excavation is done in both methods by mechanical or manual means.

Hand tunneling, open face shield, road header method and tunnel boring machines (TBM) are some of the methods used. (Read How Tunnel Boring Machines Work.)

Pipe Jacking vs. Utility Tunneling

Pipe Jacking and Utility Tunneling: Benefits and Drawbacks

Benefits of pipe jacking and utility tunneling

Pipe Jacking as well as Utility Tunneling are steerable trenchless methods that do not require excavation of trenches. They can be quickly set up and finished if planned well with relevant geotechnical investigation.

The line and grade in both methods can be well maintained and is accurate up to 1 inch of proposed line and grade. Both methods can be utilized for long lengths of pipe installation. Since the amount of spoil is restricted to the pipe diameter, the impact on the environment is low. (Read Trenchless and the Environment: How No-Dig Construction Saves Ecosystems.)

Drawbacks of pipe jacking and utility tunneling

Pipe jacking, as well as utility tunneling, can be costly for small lengths because of the significant investment required in equipment. Pipe jacking requires skilled personnel to carry out the installation.

Dewatering of tunnel path is usually required in both methods. Pipe jacking, as well as utility tunneling, may face trouble if big boulders or very hard rocks are encountered. Since pipe jacking depends entirely on the hydraulic thrust, such sub-surface features may lead to failure of the project; geotechnical investigation therefore is a very crucial part of the project.

Both methods work best in stable and consistent granular and cohesive soils. The pipe materials used in pipe jacking should be able to withstand high compressive forces that will act on it during the process. Both methods are recommended for pipe sizes 42” and larger because of logistical and safety considerations.

Typical Components

Utility Tunneling

  • Jacking pit
  • Tunnel support
  • Skid base
  • Power pack
  • Generator
  • Ventilation blower
  • Crane
  • Laser
  • Laser target
  • Tunnel boring machine
  • Conveyor
  • Dirt buckets
  • Haul unit
  • Thrust section
  • Tunnel liner

Pipe Jacking

  • Jacking pitS
  • Skid base
  • Power pack
  • Generator
  • Ventilation blower
  • Bentonite pump
  • Mixing and separation plant
  • Crane
  • Laser
  • Laser target
  • Boring machine
  • Jacking pipe
  • Dirt bucket
  • Conveyor
  • Telescopic cylinders
  • Thrust block
  • Thrust ring
  • MCB control desk
  • Haul unit
  • Intermediate jacking station (IJS).

Installation Considerations

Utility Tunneling and Pipe Jacking are trenchless construction methods with some similarities and differences. Irrespective of these, priority should be given to thorough geotechnical investigation in order to determine the most suitable method for the prevalent site conditions.

Appropriate soil testing and laboratory analysis along with reconnaissance and data study should be carried out for every project. When choosing either of these methods, ground and soil conditions are very important.

Accuracy of line and grade is crucial when installing gravity sewers that depend on slope for effective drainage. Dewatering is often essential because the launch pit often goes below the water table. Some job sites may have constraints due to environmental restrictions and physical obstructions on the surface.

Due attention should be paid to all factors before deciding on a trenchless method.

Share This Article

  • Facebook
  • LinkedIn
  • Twitter

Written by Tabitha Mishra | Civil Engineer, Technical Content Writer

Tabitha Mishra

Tabitha has a Bachelors Degree in Civil Engineering from Mumbai University, India, and is currently freelancing as a technical content writer. Prior to writing, she has worked as a site engineer and site manager for various building construction, building rehabilitation, and real estate evaluation projects.

Tabitha is also certified as a Primavera project management professional and is well versed with Auto CAD. In her spare time, she does private consultation for small-sized home builders and assists with plans and permissions.

Related Articles

Go back to top